Industrial
Manufacturing facility in Germantown, WI
In spring 2023, Circle Electric was asked to provide design build services for a 294,000 square foot plastic injection molding facility in Germantown. However, the request had two unique challenges. Energy needs would be near 12,000A 480V, plus the plastic molding press equipment was arriving quickly – in June 2024.
Knowing that utility company review, approval, and construction for three building services would consume the project timeline, we decided to install customer-owned infrastructure and receive a primary voltage connection from the utility only. This minimized our dependency on the utility, which was the key to faster construction.
Underground excavation began September 2023 and Circle Electric began installing a 24.9 kilovolt gear lineup, three downstream oil-filled transformers, and three 480V 3PH 4W services (rated 3000A, 4000A, and 5000A). Power was turned on for the facility 11 months after the contract date so the customer could begin clean-room certification and start production.
Learn about the industries we serve